The C-Bus Community Forums is place where C-Bus users can share information and help others with C-Bus. From time to time you will see Clipsal staff on the forums, but this is not an official support channel. If you really need help contact the official support services of Clipsal. More information about the purpose of this forum is available here.

Reply
 
Thread Tools Display Modes
  #11  
Old 31 Mar 10, 03:22 PM
daniel's Avatar
daniel daniel is offline
C-Busser
 
Join Date: Jul 2004
Location: Adelaide
Posts: 348
Default

Toolkit 1.11.1 has been released. Announcement here.

Changes relevant to this thread:

1. Fixed C-Gate regression for sites using the project.start= config option. The networks will now open immediately instead of after 15 minutes.

2. C-Gate will now sync up to 25 parallel networks at once (instead of 5). This should improve operations at CNI-centric installations.
__________________
"Smoke me a kipper, I'll be back for breakfast!" -- A. Rimmer, Space Adventurer
Reply With Quote
  #12  
Old 31 Mar 10, 08:30 PM
more-solutions more-solutions is offline
Member
 
Join Date: Apr 2006
Location: Peterborough, UK
Posts: 56
Default

Quote:
Originally Posted by daniel View Post
1. Fixed C-Gate regression for sites using the project.start= config option. The networks will now open immediately instead of after 15 minutes.
Great, thanks! I will try when next on site (~1week)

Quote:
Originally Posted by daniel View Post
2. C-Gate will now sync up to 25 parallel networks at once (instead of 5). This should improve operations at CNI-centric installations.
How does this compare with the older version? I have 35 networks, presumably the other 10 will start as the first ones finish?

My objective, obviously, is to get all 35 networks in sync as quickly as possible. I appreciate that starting all 35 together is necessarily the best way to do that.
__________________
Mark Rogers, More Solutions Ltd
Reply With Quote
  #13  
Old 05 Apr 10, 07:43 AM
Lucky555 Lucky555 is offline
Senior Member
 
Join Date: Aug 2007
Posts: 226
Default

Quote:
Originally Posted by daniel View Post
Just touching on a few things, before receiving any logs:


Connecting to a network in TK will disable background syncs because TK sets the network property autosync=no (it is the only client application to do this). The Scan button will then do a demand sync. This takes a minute or two and you'll see the progress in TK. So if you are only using TK, sync-time doesn't have any bearing on this case.

I am not sure whether use of C-Lution sets autosync back to yes or not. A lot depends on whether it connects before or after TK. This is a fairly important point which the logs will reveal.
Hi Daniel,

The section above raises the question in my simple mind - What does Schedule Plus / Homegate do in relation to autosync= setting ?
Thanks...
Reply With Quote
  #14  
Old 06 Apr 10, 10:21 AM
Darren Darren is offline
Senior Member
 
Join Date: Jul 2004
Location: Adelaide, South Australia
Posts: 1,830
Default

Quote:
Originally Posted by Lucky555 View Post
The section above raises the question in my simple mind - What does Schedule Plus / Homegate do in relation to autosync= setting ?
They use autosync. The sync period is defined in the C-Gate configuration file.
__________________
Regards,

Darren
Reply With Quote
  #15  
Old 06 Apr 10, 06:37 PM
more-solutions more-solutions is offline
Member
 
Join Date: Apr 2006
Location: Peterborough, UK
Posts: 56
Default

Quote:
Originally Posted by more-solutions View Post
My objective, obviously, is to get all 35 networks in sync as quickly as possible. I appreciate that starting all 35 together is necessarily the best way to do that.
Just realised I wrote that wrong. Obviously (I hope) what I meant was:

I appreciate that starting all 35 together is not necessarily the best way to do that.
__________________
Mark Rogers, More Solutions Ltd
Reply With Quote
Reply

Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is On
Forum Jump

Similar Threads
Thread Thread Starter Forum Replies Last Post
Homegate losing network sync 0/1 networks krowie C-Touch/HomeGate/SchedulePlus/PICED 3 18 May 09 11:21 AM
PCI sync failed - normal? ssaunders C-Bus Toolkit/C-Gate 1 13 Jan 09 04:24 PM
C-Gate 2.3 Network Sync Issue Duncan C-Bus Toolkit/C-Gate 11 13 Oct 05 07:39 PM


All times are GMT +10.5. The time now is 11:09 PM.


Powered by vBulletin® Version 3.7.4
Copyright ©2000 - 2010, Jelsoft Enterprises Ltd.