Charlie Crackle
31 Oct 04, 01:13 AM
When you click on the network on the project manager you get a nice little summary about the:
Current Consumption
Current Supply
Impedance
Units Calculated
Units Not Calculated
Result.
A great little cbus calcualtor....
Question
If you start a new project in tool kit 1.1 it all works great the Units Calculated = number of units and all calcs look good.
If you import a project all the items go to the "Units Not calculated" if you add some new ones they go to "Calculated"
What is the procedure to do a calculate...on an imported project.
Charles
Duncan
31 Oct 04, 08:53 AM
When you click on the network on the project manager you get a nice little summary about the:
Current Consumption
Current Supply
Impedance
Units Calculated
Units Not Calculated
Result.
A great little cbus calcualtor....
Question
If you start a new project in tool kit 1.1 it all works great the Units Calculated = number of units and all calcs look good.
If you import a project all the items go to the "Units Not calculated" if you add some new ones they go to "Calculated"
What is the procedure to do a calculate...on an imported project.
Charles
Hi Charles,
To be included in the calculation each unit must have its catalog number provided, which you can provide if you open up the "UI" for each unit. This is because some units such as those that MAY or MAY not have a power supply cant be determined through software alone (they look identical on the network).
That being said, we are planning to provide a 'default' catalog number for each Unit Type on the network, which will go a long to way to improving this feature. This would mean a little bit of diligence on the part of the installer, but it should make it much more useful.
Charlie Crackle
01 Nov 04, 02:03 AM
It has taken Tooo long but I have updated all the catalogue numbers on the 44 unit network.
It now says 22 units calculated 22 units not calculated.
I have double checked and all 44 have correct catalogue numbers.
( did this by adding a new unit and noting down the catalogue number)
is there any way to work out which units are the ones not calculated ???
Charles
Duncan
01 Nov 04, 08:14 AM
is there any way to work out which units are the ones not calculated ???
Charles
Not currently.. but it looks like thats going to be an essential feature, would I be able to trouble you to email me the XML file associated with that project.. you'll find in your Clipsal\CGate2\tag\ directly?
Charlie Crackle
04 Nov 04, 11:34 PM
Did you get my tag Database ??
Charles
Duncan
05 Nov 04, 07:52 AM
Did you get my tag Database ??
Charles
Yep! working thru it.